Quality_Assurance_Inspection

Quality Assurance Inspection

*Required
3. Is crew on the job?(Required)
4. All exterior cavities were filled with insulation

Batts

5. The correct R-Values were installed
6. The R-Value stenciling was visible
7. All water pipes were insulated to protect from freezing
8. All chases were blocked of capped
9. There are no spaces or voids between insulation and framing
10. Compression of insulation was kept to 1" or less consistently
11. All odd spaced cavities were correctly insulated
12. All windows, doors, small cracks and penetrations were air sealed
13. Insulation or foam was placed behind all electrical boxes
14. All insulation was split or cut around wires as needed
15. All insulation was attached/supported as needed (stapled as required or used correct supports such as lightning rods)
16. All areas requiring insulation have been insulated (band joists, knee walls, overhangs/cantilevers protruding beyond exterior walls)
17. All attic baffles or chutes were installed correctly
18. Insulation was installed over the top plate of walls as needed
19. Rips or tears in vapor retarders were repaired
20. The fireplace is insulated correctly
21. The job site was left clean and trash was removed
22. No materials/equipment were left on the job

Attic

23. All areas of attic were blow including difficult areas such as hip corners and over the top plates
24. The insulation was blown to a depth equal to, or more than the required thickness
25. The insulation was blown level
26. The attic rulers were visible
27. All ceiling penetrations were air sealed
28. The eave vents/baffles were free of insulation
29. All chases were capped or blocked
30. Clearances were maintained around fossil fuel appliances, metal chimneys, and fireplaces
31. A clearance of 3" or greater was maintained around non-IC rated fixtures
32. The scuttle or attic stairway hole insulated and sealed
33. The area was cleaned up and trash disposed of properly
34. The minimum or greater number bags required by the manufacturers label were installed
35. A COMPLETE ATTIC CARD was attached near the scuttle home (Job Name, Date, Type of Construction, Number of Bags, Area of Coverage (sq. Ft.), Depth of Previous Insulation, Installed R-Value, and Installer Name/Signature)
36. No materials/equipment were left on the job

Blown-In Walls

37. All exterior cavities were filled with insulation
38. All water pipes were insulated to protect from freezing
39. All chases were blocked or capped
40. There are no spaces or voids between insulation and framing
41. All odd spaced cavities were correctly insulated
42. All windows, doors, small cracks and penetrations were air sealed
43. Insulation or foam was placed behind all electrical boxes
44. All areas requiring insulation have been insulated (band joists, knee walls, and overhangs protruding beyond exterior walls, cantilevers)
45. The insulation is not bridging the face of the studs
46. All insulation was broomed to be flush with the face of the studs
47. Density/coverage was checked as the installation progressed
48. Rips or tears in vapor retarders were repaired (if applicable)
49. The fireplace was insulated correctly
50. The job site was left clean and trash was removed
51. No materials/equipment were left on the job

Air Sealing

52. Windows and doors sealed properly
53. All wire penetration sealed properly
54. Sealed properly behind all boxes in walls

Spray Applied Foam

55. Building cavities filled to proper thickness
56. Foam sprayed to proper R-Value/Thickness
57. Spray foam adhesion to all sides of the cavity
58. Pipes and wires encapsulated in foam
59. Electrical box interior free from foam
60. All foam shaved flush with stud face (if necessary)
61. Spray foam at least 3" from non-IC rated can lights
62. Spray foam at least 3" from chimneys and flue pipes
63. Crawlspace walls are sealed from top to bottom
64. Crawlspace floor covered with 6mil or > poly
65. Where needed, thermal or ignition barrier is installed to proper mil thickness
66. On-ratio foam has been installed
67. No shrinkage or delamination of foam present
68. Stroke count has been recorded on worksheet
69. Entire house has been inspected for overspray & removed where necessary
70. Proper PPE has been worn properly during the entire job
71. All foam installed per work order and manufacturer's recommendations
72. The job site was left clean and trash was removed

Head of Wall

73. Gap is stuffed such that there are no spaces or voids between drywall, structural penetrations decking above
74. Adequate compression of insulation is maintained
75. All odd spaced cavities were correctly stuffed
76. All walls to be sprayed are done so with correct types of sealant
77. Any overspray has been removed as necessary
78. Spray overlaps walls and decking by 1"-2"
79. Sealant applied to proper mil thickness
80. All areas requiring stuffing/spray have been stuffed/sprayed properly according to work order
81. The jobsite was left clean and trash was removed
82. No materials/equipment were left on the job

Edge of Slab

83. There are no spaces or voids between floor and exterior sheathing
84. Adequate compression of insulation is maintained
85. All odd spaced cavities were correctly insulated
86. All areas requiring edge of slab fire stopping have been stuffed and sprayed appropriately according to work order
87. Spray has adhered to stuffing
88. Spray overlaps floor and exterior sheathing by 1"-2"
89. Any overspray has been removed as necessary
90. The jobsite was left clean and the trash was removed
91. No materials/equipment were left on the job

Roll Material

92. Proper overlap
93. All penetrations or tears are properly taped
94. Touching bottom of floor truss
95. Cut properly around doors and windows
96. Pin shot minimum of every 6', straight and pulled tight

Notes & More

MM slash DD slash YYYY