HSHS St. Elizabeth’s Hospital

St Elizabeth's Hospital



CASE STUDY

HSHS St. Elizabeth’s Hospital


The Need


A subcontractor was sought to apply insulation in new patient rooms at a regional hospital. To ensure patient privacy and meet rigorous regulations, sound control was a very significant factor in the final deliverable.


The Goley Solution

Goley’s competitive bid detailed how we had the manpower and processes to meet the third-party regulations and timeline constraints. We secured the job and stepped up to deliver a comprehensive solution for our customer.

We completed the work in two phases:

PHASE 1: We insulated interior sound walls, which involved splitting the fiberglass batt insulation at the stacked metal studs (e.g., doors, windows, etc.). This was needed to ensure proper sound control and meet the stringent third-party quality regulations.

  • Our installers packed the fiberglass insulation between stacked metal studs at the door jams. This required the jams to be carefully pried apart and chinked with material on every door.
  • Our teams meticulously worked around a variety of obstruuctions including oxygen lines, medical gas and electrical conduit.

PHASE 2: We applied closed cell spray foam with an intumescent coating at various scattered exterior wall locations. The scale of the job necessitated application from the roof, approximately 60 feet up.

Throughout the duration of this project, we had the knowledge and experience to tackle a range of challenges—including the sequencing of the job, extreme weather conditions, unique application specifications, and third-party inspections.

Highlights include:

  • We provided consistent communication and collaboration. The continual inspections meant that Goley’s crew needed to work closely with the inspectors and our customer to meet regulations every step of the way.
  • We quickly assembled to apply products within the timeline constraints. The timing of this project meant our crews had to work in cold and often wet weather conditions. This presented a challenge, since spray foam must be applied at a certain temperature substrate and should not be applied in high wind conditions. Thus, our crews needed to mobilize quickly to apply the products when the conditions allowed for it. We promptly delivered the materials to the jobsite and successfully applied them in challenging conditions.
  • We remained detail-oriented and thorough in a fast-paced, demanding environment. Multiple drywallers were on the jobsite throughout this project. Thus, our installers often needed to rearrange their workflow to accommodate them—by moving tools, equipment, materials, etc. Yet, although they often had to shift their focus and respond to the conditions around them, our meticulous crews never sacrificed quality.

“I was glad that Goley was on this job. The third-party inspections were intensive—especially for sound insulation. Additionally, it was a very fast timeline. Goley’s foreman worked closely with ours, as well as the third-party inspector, every step of the way. Whenever there was an issue, Goley quickly fixed it.”

st E
st E


The Result

Goley was able to successfully meet the demanding timeline with the proper products. This was a highly sensitive environment, both from a security and application standpoint. Continuity was also a major factor; only the same crewmembers were expected on the job. Our installers were punctual, professional and clean on the jobsite. The customer reports being satisfied with how the insulation helped to improve the indoor environment and overall aesthetics of the facility.

St E Hospital

Project Details

+11,000 sq./ft. Closed Cell Foam

Aug 2016 – Jun 2017

+460,000 sq./ft. Fiberglass

144 Beds

+352,000 Gross sq./ft.

12 Crew Members

Download Case Study