Centene University & Daycare

Centene



CASE STUDY

Centene University & Daycare


The Need

This project involved installing insulation in an existing historical building and addition for a large educational center in downtown Clayton. Sound attenuation was a key client need, since the university wanted to ensure privacy and security from room to room.


The Goley Solution

This project required a mobile and agile crew that could adapt to timeline shifts and work in a fast-paced setting.

Goley’s comprehensive solution included:

  • Stocking material multiple stories in the air and pinning material to substrates rather than placing between framing members
  • Applying insulation behind crisscrossed framing
  • Applying R30 roll batt insulation on a concrete floor rather than blowing
  • Pinning R30 batts to the attic side of mechanical mezzanine walls
  • Installing R19 insulation in walls, as well as a large amount of head of wall sealing, edge of slab firestopping, and mineral wool


Goley went above and beyond to provide:

  • Necessary manpower: To accommodate the fast pace of the job, Goley supplied additional manpower and hours to ensure the high-performing products were applied on time and within budget. Additionally, because this was a historical building, additional building codes were involved. These regulations often caused overall project delays. However, Goley had the proper manpower coverage to offset any timing setbacks.
  • Expertise: Due to design nuances and specifications, the work necessitated applying out-of-ordinary materials in unique applications.
  • Mobility: The downtown location, which was in a neighborhood, necessitated that a contractor could work through logistical challenges, such as scheduling and delivering materials to the jobsite. Goley worked within limited time constraints to make the work happen.
  • Focus and collaboration: To meet timeline shifts, there were many trades on the job at once—so it was critical that the insulation subcontractor could effectively work alongside others. Our crewmembers are well-versed in maintaining focus in fast-paced, demanding settings.

“When we use Goley, we have dependability. They don’t leave anything out when they complete a bid, and they are easy to communicate with. They make sure the men are there when we need them there on the job.”

Centene
Centene Insul


The Result

  • Accommodated timeline shifts by placing more installers on the jobsite and working overtime
  • Worked alongside many other trades on the job
  • Effectively applied a range of special order materials

This work was completed for a large interior contractor that we’ve been partnering with for decades. They reported complete satisfaction with the job, and there were no callbacks.

Project Details

+35,000 sq./ft. of Rockwool

Oct 2018 – Jun 2019

4 Crew Members

+6,000 l./f. Fire/Acoustical Head of Wall Sealant

+100 rooms

+57,000 Gross sq./ft.

+66,000 sq./ft. of Fiberglass

3 Stories